PSM 1 – Additional Practice Questions 2 Fee: Free Practice Tests (based on Scrum Guide https://www.scrum.org ) Passing score: 95% Time limit: 40 minutes Number of questions: 49 Format: Multiple Choice, Multi Answer and True/False Difficulty: Advance You have 40 minutes to pass the Assessment Test. PSM 1 - Additional Practice Questions 2 1 / 49 When does it gives the whole team a chance to communicate, to consider their progress, and to adapt what they are doing. Sprint Review Sprint Retrospective Daily Scrum Sprint Planning 2 / 49 A) The Team demonstrate the new increment to stakeholders and get their feedback.B) The team can highlight any new features and show how they relate to the product backlog items.These tasks are done as part of _________________. Sprint Review Sprint Backlog Sprint Retrospective Product backlog refinement 3 / 49 Can the team add or remove items from the product backlog into a backlog for the sprint to satisfy the Sprint Goal? False True 4 / 49 What is the Time-box for the Sprint Retrospective? 2 hours 3 hours 1 hour As long as required 5 / 49 When the team inspect and adapt the ongoing work of the sprint during the daily Scrum will result in _______________. updating the Sprint Backlog updating the Sprint Plan updating the Product Backlog updating the Sprint estimates 6 / 49 How much work must a Scrum Team do to a Product Backlog it selects for a Sprint? The best amount of work the Team can do given that is usually impossible for QA to finish all of the testing that is needed to prove it can be shipped. All of the analysis, design, development, testing and documentation work. As much work as the Team can fit into a Sprint. As much work as it has told the Product Owner will be done for every Product Backlog item it selects. 7 / 49 The Development team creates a plan for how they are going to improve things for the next Sprint, this is done as part of ____________. Sprint Planning Sprint Retrospective Sprint Review Tracking Metrics 8 / 49 Who in collaboration with the team, refines the backlog on a continual basis. The Scrum Master The Product Owner The Development Team Stakeholders 9 / 49 What are the outputs of the Sprint Review process?A) Feedback from StakeholdersB) A revised Product BacklogC) New Product IncrementD) The Sprint Backlog A and C A, B and C All the above A and B 10 / 49 Who must conform to the definition of done? The Scrum Team The Development Team The QA Department The Product Owner 11 / 49 The Development team response to what have we delivered so far is referring to __________________. the latest product backlog the latest product increment the latest sprint backlog latest spring plan. 12 / 49 When should the Product Owner ship or implement a Sprint increment? Whenever the increment is free of defects. When it makes sense. When the Team feels is done with every Sprint. At the end of every Sprint. 13 / 49 The Time-Box limit for a 1 month Sprint is______. 15 minutes 8 hours 4 hours 3 hours 14 / 49 During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog? When the Product Owner identifies a new work. When the Scrum Master has time to enter them. As soon as possible after they are identified. During the Daily Scrum after the Development Team approves them. 15 / 49 Scrum owner does not run the Scrum. False True 16 / 49 Stakeholders and the development team review and update the product backlog. The revised backlog becomes the starting point for planning the next sprint. This is done as part of ________________. Sprint Planning Release Planning Sprint Retrospective Sprint Review 17 / 49 Based on the sprint goal and who is available to deliver it the team can then decide how much to take on. False True 18 / 49 This meeting is about 'walking the board' rather than having individuals report progress. Product Backlog review Sprint Review Daily Scrum Sprint Retrospective 19 / 49 The goal of the Daily Scrum meeting is __________________________. update the spring plan. update the product owner. Inspect and adapt the ongoing work of the sprint. get to know the team members. 20 / 49 What have we delivered so far?What is still to be done?These two inputs helps the team decide_____________________. what the most important things are to work on next. outstanding items on product backlog. what to work on next sprint. the update to the product backlog. 21 / 49 What is the output of a Sprint Retrospective?A) An improvement planB) How they completed the work over the last SprintC) What went well and where there are areas of improvement All the above B A A and B 22 / 49 Who is invited to the Sprint Review meeting?A) Product OwnerB) Development TeamC) Stakeholders A, B and C A and B B and C A Only 23 / 49 The discussion with stakeholders and the chance to adapt the product backlog is a vital a part of the ________________. Sprint Retrospective Daily Scrum Product Backlog update Sprint Review process 24 / 49 Setting up the  ______________ meeting for the same time and place each day makes it as easy as possible for everyone in the team to plan to attend. Daily Scrum Sprint Review Sprint Retrospective Product Backlog review 25 / 49 Which topics should be discussed in the Sprint Review? Sprint results All the above the process coding practices 26 / 49 ___________is the plan how the team will deliver as part of their Sprint Goal. The Product Backlog Project Plan The Scrum Review Plan The Sprint Backlog 27 / 49 Which statement is an incorrect assessment of the Product Owner? The Product Owner is one person not a committee. The Product Owner prioritizes the Product Backlog The Product Owner plays a dual role: Product Owner and Scrum Master. The Product Owner is the only person responsible for the Product Backlog. 28 / 49 Backlog items cannot be more complex or should not have other dependencies. False True 29 / 49 The work needed to review and update the Scrum Artifacts should take no more than about _____ of the effort of the team. 20% 15% 5% 10% 30 / 49 The Scrum Master has these responsibilities:A) They make sure the meeting happens.B) They make sure that no-one who is not part of the team attends.C) They help the team learn to keep the discussion to the 15 minutes. A and B A, B and C B and C A and C 31 / 49 What have we delivered so far?What is still to be done?These two things helps the team in ______________ aim for the next Sprint. updating the Sprint backlog updating the Sprint Retrospective updating the Product Backlog drafting a 'Sprint Goal' 32 / 49 What are the inputs to the Sprint Retrospective meeting?A) Previous improvement actionsB) The Product BacklogC) The Sprint BacklogD) Any tracking metrics or notes gathered during the sprint B, C and D A and C All the above A, B and D 33 / 49  ______________is a list of items that the team has committed to working on and delivering during the Sprint Product Improvement Product Backlog Sprint Backlog Product refinement list 34 / 49 The transparency and inspection of:What happened yesterday?What is the plan for today?Are there any impediments / blockers?is part of ___________________. Daily Scrum Sprint Retrospective Sprint Review Sprint Planning 35 / 49 Since the time for the Scrum Meeting is so tight therefore the meeting is focused it needs constraining to only the people doing the work. True False 36 / 49 Which of the below are main Scrum roles in a Scrum Team? Development Team, Product Owner, and Scrum Master. Product Owner and Customers. Team, Users, and Competitors. ScrumMaster, Customers, Product Owners, Stakeholders, Developers. 37 / 49 The Development team cannot prioritize, scope or descope work from the sprint. True False 38 / 49 Who is responsible to answer any new questions the team may have? Development Team Scrum Master Product Owner Stakeholders 39 / 49 The adjusting part to the Scrum is something that the relevant smaller sub-groups can discuss after the scrum meeting. False True 40 / 49 The __________TeamUnderstand what they are planning to deliver.They can explain how they plan to deliver a working product increment. Product Owner Project Team Development Team Scrum Team 41 / 49 The Daily Scrum Meeting:A) Focusing on the items re-enforces that the team owns all the items.B) Makes sure the team considers all the items.C) Collaboration and support should be a strength of a motivated team.D) Focusing on the result by the whole team gives this an appropriate importance and value. B and D A, B and D All the above A and B 42 / 49 When does Scrum team membership change? Every Sprint to promote team learning Whenever management tells the Scrum team. As needed, while taking into account short term reduction in productivity. Never, because it reduces productivity. 43 / 49 Daily Scrum meeting is a time-box meeting scheduled for ____________. 30 mins 5 mins 15 mins 10 mins 44 / 49 Sprint Retrospective is time-box for _________ hours for a 1 month Sprint. 3 9 4 8 45 / 49 Who is responsible to ensure increment meets the Sprint Goal and delivers the capabilities of the Product Backlog items in scope. Scrum Master Product Owner Development Team Scrum Team 46 / 49 Scheduling the Daily Scrum meeting is the responsibility of ________________. Scrum Master Development Team Scrum Team Product Owner 47 / 49 When does the Sprint Review happens _______________. before the Sprint planning. at the beginning of the Sprint at the end of a Sprint after the Sprint Retrospective 48 / 49 Who is responsible for conducting the Sprint Retrospective meeting? Stakeholders Scrum Master Product Owner Development Team 49 / 49 What is still to be done is referring to ___________________. the current sprint plan the current sprint backlog the current product backlog the current release plan Your score is The average score is 69% LinkedIn Facebook Twitter 0% Restart quiz